Friday, 03 November 2017 14:00

Winter stops Highway #10 project, 80% complete

Contractors rushed to finish laying asphalt on Wednesday, November 1 as the snow fell around them all day. Leaf blowers were used to remove fresh snow from the road while asphalt was being laid. The project is about 80% complete, and will be staying that way until spring.       Contractors rushed to finish laying asphalt on Wednesday, November 1 as the snow fell around them all day. Leaf blowers were used to remove fresh snow from the road while asphalt was being laid. The project is about 80% complete, and will be staying that way until spring.       Photo by Anna Latimer

Despite the best plans of mice and men, Highway #10 will not be completed in 2017. Manitoba Infrastructure and Transportation is finishing up what it can for the winter and planning to get right back at it next spring.

Since July, contractors have been working on the stretch through Boissevain, as well as pieces to the north and south. There have been a few weather delays, including rain and snow, and so completion is not possible. But, according to Herb Mahood, Director of Regional Operations for MIT, everything should be safe and ready for the next season.

“Right now,” Mahood said on Wednesday, “we are working at getting the asphalting on the majority of the vulnerable area. In the next couple of days we will pave as much as possible.”

A crew member uses a leaf blower to remove fresh snow from the #10 highway in Boissevain ahead of the asphalt being laid. The highway improvement project through town is about 80% complete, and due to of cold weather, it will not be completed until spring.

He said all except the part right in front of the school should have at least one layer – or lift – of pavement on it. Some parts have two. That will hold it through the winter. Overall, Mahood said they are likely about 80% complete on the project, which also included new curbs and gutters along the highway in town. The new entrance to the health centre also has seen a great deal of work.

As a good dump of snow is predicted for Saturday, they have to be packed up and gone by then. They will be back when the weather is suitable in the spring. Mahood said the contractor, Borland, will want to get in and out as soon as possible in 2018 to move on to other projects. He asks the public to bear with them for the rest of the week.

“You like to start a job and finish it at once,” he said, “but it doesn’t always work that way. We will be back in the spring and everything should be safe for winter.”

by PAUL RAYNER, Recorder staff

 

 

 